Equipment Guide · Cargo Level Gauging & Overfill Protection

Cargo Level Gauging & Overfill Protection — Two Alarms Between You and Oil on Deck

A tanker loads blind: the tank is sealed, the atmosphere is inert, and the only knowledge of how full it is comes from the gauging system. This guide follows the measurement from the radar antenna on the tank top, through the ullage arithmetic, to the two alarms — the 95% working alarm and the fully independent 98% overfill fork — and then into the topping-off discipline that makes the last metre routine instead of an emergency. Tap a step or press “Play”, then try to top off a tank yourself in the simulator.

ullage · alarms: closed · inerted · 3,000 m³/h
cargo control room deck / cargo tank liquid surface displaced vapour out (alarm marks exaggerated for clarity) cargo tank — 10,000 m³ · depth 20 m radar ullage gauge sealed · no moving parts datum ullage 7.10 m FROM ULLAGE TO VOLUME level = depth − ullage volume ← ullage tables (trim & list) 95% H — gauge-chain alarm 98% HH — independent fork CCR — GAUGE DISPLAY ULL 7.10 m · 64% gauge chain · drives the 95% alarm OVERFILL ALARM PANEL 98% HH lamp + horn independent power supply own cable from manifold · loading drop line
Step 1 / 9

A tank you cannot look into

Loading…

Key —
Tap a step
From alarm to oil on deck — a worked clockt = 60 × V ÷ Q
Common mistakefinishing at the bulk rate “to save time” — from the 95% alarm at 3,000 m³/h you hold 10 minutes; one phone call and half of it is gone.

The same 200 m³ of remaining space is four minutes at the bulk rate and twenty-four at a staged topping rate of 500 m³/h. The reduction does not slow the operation in any way that matters — it buys time back in exactly the window where overfills happen. That is the entire logic of topping-off discipline: the 95% alarm opens a ten-minute window at worst, and every stage of rate reduction stretches it. Run t = 60 × V ÷ Q for your own tanks before the loading starts — that arithmetic belongs on the loading plan, not in your head at 02:00.

Working principle — explained in our own plain words with our own schematic from general marine knowledge (not copied from any OEM manual). Conceptual; varies by ship/model. Reviewed and verified by a Master Mariner.